Short Answer
The average lead time for linen clothing manufacturing is typically 30–45 days for bulk production after sample approval. For new developments or highly customized styles, lead time can extend to 45–60 days.
Lead time is calculated from PPS (Pre-Production Sample) approval, not from the first inquiry or sampling request. This ensures accurate planning and realistic delivery expectations.
| Production Stage | Typical Timeframe | Notes |
|---|---|---|
| Tech pack & order confirmation | 3–7 days | Size chart, BOM, trims locked |
| Fabric preparation & dyeing | 7–14 days | Linen requires pre-wash & stabilization |
| Cutting & sewing | 10–20 days | Depends on SMV & order volume |
| Washing & finishing | 3–7 days | Shrinkage control is critical |
| Final QC & packing | 3–5 days | AQL inspection & carton preparation |
| Total bulk production | 30–45 days | Industry average |
| New development / complex styles | 45–60 days | New patterns or special finishes |
Linen production is slower by nature, but it delivers superior durability, breathability, and premium value.
| Region | Average Lead Time | Characteristics |
|---|---|---|
| China | 30–45 days | Efficient scale, flexible MOQ |
| Eastern Europe | 40–60 days | Smaller batches, higher labor cost |
| Western Europe | 50–75 days | Artisanal focus, premium positioning |
At Linenwind, our production timelines are structured for reliability and transparency:
Our systems include European flax linen pre-booking, in-house CAD and sampling, low MOQ support, and milestone-based production scheduling.
Explore our OEM & ODM linen manufacturing services, browse custom linen product collections, or request a production timeline estimate.